1. Minimum configuration to post a journal in FI:
(The
assumption is that you do not want to copy either the standard SAP company or an
existing company code because it will copy across too much that is not similar
or not required and therefore too much cleanup will be required).
Initial Business Decisions Required:
Item to be
decided
|
Comment
|
Code of company
code (4 Digit Alphanumeric) |
You could setup
new one later, copying the configuration
|
Code of Chart of
Accounts
|
Not very visible,
but the maintainers of the chart may want to decide this name
|
Length of the GL
A/c number and the account number range guidelines, possibly also the numbers of
some key accounts required for automatic postings (see below)
|
SAP allows 10
digits, however 5-7 appears to be the normal range.� Typically the number of
accounts should be in the low hundreds.�� Decide on the ranges of numbers for
each type of account as much as you can so that the team can start getting used
to them. EG: standard SAP usually has 4xxxxx as expense accounts, 11xxxx as Bank
Related accounts etc.�� |
Configuration steps:
Step
|
Comment
|
Define the
company code
|
IMG
|
Define the name
for a chart of accounts |
IMG
|
Maintain the
global parameters |
IMG - Use
standard SAP variants for the parameters to start with & update
later
|
Define the
default amount tolerances |
IMG - Define for
a blank group - so any new test user can post during prototyping
|
Define document
number ranges |
IMG - Copy from
the standard ranges
|
Create some of
the minimum accounts needed to start off with.� |
GL Master
data: A/R and A/P control a/cs, a petty cash or suspense a/c to hold sundry
offset postings while debugging, a revenue account, some expense accounts.� This
list will expand as you go - see the section on account determination.
Suggest you create with reference
from the standard chart and company code and use those specifications (account
groups, fields status groups etc)� for now, so that these accounts will be
reasonably appropriately setup.
|
Now
you should at least be able to post a GL journal. To test I suggest you use
balance sheet accounts only, since you will not have setup the cost elements for
the expense accounts. All projects would at least be using the Cost center and
Cost Element functionality of CO as a minimum.� So - on to the next step.
Initial Business Decisions Required:
Item to be
decided
|
Comment
|
Structure of
standard cost center hierarchy
|
The structure
should follow the organizations intended responsibility reporting hierarchy (the
budgetary responsibility).� Allow the appropriate number of levels.
|
Hierarchy node
name coding
|
The coding of the
nodes is quite important because they can be used to report on the levels in the
standard reports, and so will be very visible to the users
|
Cost Center Naming Standards
|
Useful to begin
following the intended standards ASAP so that test data looks as real as
possible.
|
Configuration steps:
Step
|
Comment
|
Define the
controlling area
|
IMG, not very
visible to users, if you are only going to have one, you could default
it later
|
Assign the
company code to the controlling area
|
IMG
|
Create the
beginnings of the standard cost center hierarchy
|
CO -
Cost Center Master data
|
Create a
representative set of cost centers, assigning them to the appropriate node in
the cost center hierarchy
|
CO -
Cost Center Master data
|
Create all the
expense accounts as primary cost elements
|
Either in the IMG
- for all GL accounts in a specific range, or individually in the CO - Cost
Center Master data
|
Now
you should be able to post a GL document (journal) to an expense account and
code it to the cost center.� The posting should then be viewable via
Cost Center reporting and GL Account line Item Display.
3. Minimum configuration to post to sub ledgers (AR, AP)
Initial Business Decisions Required:
Item to be
decided
|
Comment
|
GL Account Number
of Control accounts
|
see account
number range comments above
|
Configuration steps:
Step
|
Comment
|
Create the AP and
AR Control accounts in the GL
|
see account
creation comments above
|
Create a couple
of customer and vendor accounts
|
If using SD and
MM too, inform the SD and MM analysts so that they can complete the account
creation on the SD/MM side for the customer and vendor respectively.
|
Now
you should be able to post a FI-AR customer invoice and an FI-AP vendor
invoice.
4. Minimum configuration to post from logistics modules to FI/CO (similar
concept for other modules)
So
far it was relatively easy going, now it starts getting a little more
difficult.� Following are the very broad steps - for more detail see the
sections on Organization
structure and Integration.
Initial Business Decisions Required:
Item to be
decided
|
Comment
|
SD and MM
organization structure and relationship to the FI/CO elements
|
Not a trivial
decision, and may require rework, so at this stage, decide on a simple best
guess with the SD/MM team to get you going
|
Configuration steps:
Step
|
Comment
|
Assign the SD and
MM organization
elements to the FI/CO elements
|
IMG; to get
prototyping going you need at least 1 set of working relationships that the
whole team can work with (EG: 1 Sales Area, 1 Purchasing Organization, 1 Plant
etc)
|
Maintain the
basic automatic
account determination for each module
|
IMG; For example
: Revenue Account Determination for SD.� As the modules test or prototype
expanded functionality, the SAP will look for the accounts to which it should
post.� You could maintain on an as needed basis. The SAP documentation and
configuration does not always explain clearly which piece of account
determination is used for which type of functionality, so it is sometimes
difficult to be pro-active.� being reactive has the benefit that hopefully each
side (e.g.: MM and FI) can develop an understanding of what the business
transaction is and therefore where it should be posting. Otherwise the MM person
may not even be aware that he has generated a certain type of posting ! (You'd
be amazed at some of the lack of ownership from a logistics consultant for the
financial postings that they generate).
|
Now
the other modules will be able to process a thin 'path' using agreed
organization elements and base functionality, all the way through to FI.
|