Assign Multiple Planned Order to a Purchase
Requisition
In order to assign multiple planned order to a single purchase
requisition number, you need to make used of the external purchase requisition
number range.
Define your external purchase requisition number range in
OMDN.
Assign the external purchase requisition group number range to used
in OMI3.
Once the IMG settings are completed, you can used
MD15 to assign the multiple planned order into
a single purchase requisition number.
In MD15, select the planned order you want
to convert to a purchase requisition.
Next, click the Convert Online button.
SAP will display the planned order in change mode.
Now, look for the Purchase Requisition
fields and supply the Purchase requisition
number.
For example, assuming that you assign the external number range 2000001.
In the planned order, you type the first number range 2000001 and item number 10
subsequently, copy and paste the number range but input the item number
manually.
It would be like 2000001 10 and save
2000001 20 and save.....
The disadvantages is that the user have to track and enter the external number
range manually.
Therefore, there is a trade off, between
1. having a single planned order for a single purchase requisition number or
2. having multiple planned order to a single purchase requisition number.